Last doors were installed this week
Sun, 20 Sep 2026 9:32:00 UTC


Wednesday this week the team as well as the door supplier were back at the house to install the last doors. The last doors were all interior apratment doors in the groundfloor apartment. The team installed the doorframes Wednesday and doors came up during Friday.

After that the missing baseboards (rodapes) were installed. These are the rodapes that are aligned with the door frames in each slot and are always installed af the doors, frames and the door slot boards are all installed.
Also Wednesdays the black smith came to install the new door lock and do some filling for the old removed lock.

During Thursday there was an infernal noise through out the house. The team was busy removing the old remaining frontdoor glass parts. There are new pictures of the frontdoor glass parts in the photo archive. Photos of old glass parts being removed and the new glass parts being installed.

Photos of the new installed frames and doors from the photo archive.